Progress Photographs

1. A view showing the demolition
of a bridge and part of the existing culvert for the River Trent and Fowlea
Brook at Whieldon Road. The work is necessary to enable the completion of the
tie-in of the new open channel that runs adjacent to Maclagan Street.


3. The
construction of a new culvert for the River Trent and Fowlea Brook south of
City Road junction. This new section of culvert will divert the rivers under
the realigned A500 to tie-in with the open channel adjacent to Maclagan Street.

4. A view
looking north of the temporary City Road junction showing traffic on the recently
constructed over bridge for the future A500 underpass. The work being undertaken
beneath the bridge is the construction of an open channel for the River Trent
and Fowlea brook that will run adjacent to the southbound carriageway.

5. The construction
of an open channel for Fowlea Brook north of City Road junction. This section
ties-in with a previously constructed section of culvert that links into the
existing Fowlea Brook culvert at Brook Street.

6. A view
looking south from the Stoke Road junction showing the construction of a new
environmental barrier adjacent to the Trent and Mersey canal.

7. A view
of works beneath the new over bridge at Stoke Road junction showing the construction
of the future A500 underpass.

8. A view
looking south across the new temporary Stoke Road junction. Works being show
include piling for the realignment of the Trent and Mersey canal that will see
the canal back on its original alignment.

9. A view
looking north along the recently constructed channel for Fowlea Brook north
of Stoke Road junction adjacent to the Milton Hollins building.